Major work on the construction and improvement of the play area for youngsters 0 to 6 began in early spring.

 

Two new activities will open at the end of June :

Île des aventuriers

This aquatic play area of 4,500 sq. ft. and a capacity of up to 200 people will feature water games and theme-based play modules.

Brand new Île aux trésors

The wading pool for young children will be completely revamped, modernized and equipped with a mini-slide at the centre of the pool.

 

Work schedule

Week of April 17

  • Snow removal from access roads and area at the bottom of chairlift 4
  • Teardown of fences
  • Start of construction on the new rock wall in the Grand Canyon
  • Pavement breaking and start of excavation

 

Week of April 24

  • Teardown of snowmaking pipe system
  • Start of major excavation work
  • Clearing of the play area concrete
  • Installation of sediment barriers